Global Infrastructure Circle · 5 recent topics
KenyaGrace W.·Verified member · Project chief engineer2026-10-24Kenya rural road, 42 km: how to match paver and rollers?
Six-metre width, 5 cm asphalt layer, 10-month schedule.
3
UgandaAde O.·Verified member · Procurement lead2026-10-14Uganda building project: rent or buy the tower crane?
18 months, a 6015 crane rents at USD 11,000 a month with operator.
3
TanzaniaPaulo M.·Verified member · Project chief engineer2026-10-02Tanzania section with a 4-month rainy season: how to schedule earthworks?
Contract allows 20 months; last rainy season cost 40 idle days.
3
ZambiaKwame A.·Verified member · Mine equipment manager2026-09-20Zambia water pipeline, 60 km: trencher or excavator attachment?
315 mm pipe, 1.5 m depth, mostly gravelly soil.
3
MozambiqueFatou D.·Verified member · Procurement lead2026-09-05Mozambique yard project: batch concrete on site or buy ready-mix?
18,000 m³, the ready-mix plant is 25 km away and often queued.
3