Roads & municipalНигерия · Лагос2024 · около 7 месяцев

Equipment package for Lagos urban road rehabilitation

A contractor needed 32 km of road rehabilitation within one rainy-season window; the platform built a schedule-driven equipment list with local operators and parts.

Проверка сайта

A one-week delay would compress compaction and paving windows, and local parts lead times made downtime a major risk.

  • Equipment split across compaction, paving and haulage to avoid single-brand downtime.
  • Wear-part kits shipped with the fleet plus two standby rollers to cut recovery time.
  • Twelve operators matched from the local pool with model handover and safety induction.

32 km

Road rehabilitated

> 92%

Наличие парка техники

45 дней

Mobilisation

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Equipment package for Lagos urban road rehabilitation
Mining & processingЗамбия · Медный пояс2023–2025 · поэтапная поставка

Load-and-haul combination for an open-pit copper mine

Plant expansion raised stripping volumes; the platform reconfigured the fleet with 90 t excavators and 60 t wide-body tippers, adding a parts warehouse.

Проверка сайта

Truck tonnage did not match loading capacity, increasing queue time, fuel and tyre costs.

  • Truck-to-loader ratio recalculated from cycle times to cut mutual waiting.
  • Fast-moving parts pre-positioned locally with 48-hour coverage.
  • Driver fatigue management and inspection routines reduced unplanned downtime.

5 : 1

Truck-loader ratio

48 h

Parts lead time

+ 30%

Производительность вскрышных работ

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Load-and-haul combination for an open-pit copper mine
Lifting & erectionКения · Найроби2025 · около 2 месяцев

Steel structure erection for a logistics warehouse

A large-span warehouse with restricted internal roads: an 80 t mobile crane and lift plan supported night-time road closures.

Проверка сайта

The site sits in a live logistics park; no daytime road occupation, leaving a four-hour night window.

  • Pre-assembly plus panelised lifts shortened each lift cycle.
  • Load charts verified per radius, with superlift and counterweight plan.
  • Local signallers and safety officers coordinated with night lighting and exclusion zones.

1,850 t

Steel erected

4 ч / день

Night window

68 дней

Длительность

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Steel structure erection for a logistics warehouse
Ports & logisticsАнгола · Луанда2024–2025 · поэтапное поступление

Terminal tractors and handling equipment for a port yard

With rising yard throughput, the platform supplied terminal tractors, reach stackers and forklifts, coordinating port access and on-site service.

Проверка сайта

The port applies its own emission, noise and access rules, and parts must be replenished by sea.

  • Models selected against the port access checklist with early technical submissions.
  • Six-month parts forecast consolidated into vessel shipments.
  • On-site technicians covered first-year warranty and operator training.

18 единиц

Handling units

By vessel

Parts supply

12 месяцев

Сервис на объекте

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Terminal tractors and handling equipment for a port yard
Agriculture & processingЭфиопия · Аддис-Абеба2025 · около 5 месяцев

Turnkey processing line for an agro-processing plant

Cleaning, drying and packaging delivered as one line, with OEM engineers, customs clearance and commissioning coordinated.

Проверка сайта

Volatile grid power at the site required voltage stabilisation and backup planning at selection stage.

  • Motors and stabilisers configured to local voltage and frequency.
  • Segmented shipping and on-site assembly reduced handling difficulty.
  • Local crew trained for daily cleaning and wear-part replacement.

26 комплектов

Line equipment

38 дней

Commissioning

22 people

Локальное обучение

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Turnkey processing line for an agro-processing plant
Бывшее в эксплуатации оборудованиеДР Конго · Лубумбаши2025 · около 3 месяцев

Пакетная инспекция и доставка б/у автопарка

A budget-constrained buyer sourced nine used excavators backed by 128-point reports, hour verification and arrival re-inspection.

Проверка сайта

Used equipment information is opaque, making hours and structural condition hard to verify before shipping.

  • A unified checklist covering hydraulics, structure, electrics and undercarriage.
  • Hours and service records cross-checked with risk grading for anomalies.
  • Local service points re-inspect on arrival, with discrepancies handled per contract.

9 единиц

Единиц поставлено

128 points

Точки контроля

9 / 9

Arrival re-check

Читать полный кейс
ПоделитьсяFacebookXWhatsAppLinkedIn
Batch inspection and delivery of a used fleet

Опишите объект, получите исполняемую конфигурацию

Укажите местоположение, график, объем работ и бюджетный диапазон; платформа подбирает агентов и OEM-производителей по странам и предоставляет список оборудования, требования к документам и рекомендации по персоналу.

Стать сервисным партнёром

RELATED

Изучить возможности доставки