26 conjuntos

Line equipment

38 días

Commissioning

22 people

Formación local

CHALLENGE

Desafío del sitio

Volatile grid power at the site required voltage stabilisation and backup planning at selection stage.

APPROACH

Qué hicimos

  1. 01Motors and stabilisers configured to local voltage and frequency.
  2. 02Segmented shipping and on-site assembly reduced handling difficulty.
  3. 03Local crew trained for daily cleaning and wear-part replacement.